Forthcoming Roadworks in the Ealing Area
Closures and diversions which may cause problems
Nine Month Delay to Gunnersbury Avenue Roadworks
Power Road bridge project lane closures to continue until autumn 2018
Longfield Avenue, Ealing |
01 October — 29 October |
Delays likely Road closure |
Works description: To install 1x HV duct in footway and carriageway, will also need to do a road crossing outside substation. |
Responsibility for works: GAS TRANSPORTATION CO LTD |
Current status: Planned work about to start |
Works reference: ZP011P-0095574/R2 |
A40 Western Avenue, Perivale |
08 October — 11 October |
Delays likely Lane closure |
Works description: CARRIAGEWAY PATCHING REPAIRS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG430327669 |
|
B452 Northfield Avenue, West Ealing |
08 October — 17 October |
Delays likely Traffic control (Stop/Go boards) |
Works description: 2X JOINT HOLES AND 18M OF TRENCH. VANS WILL BE PARKED IN BAYS NOT OBSTRUCTING THE FLOW OF TRAFFIC. Stop and go may be needed FOR THE GRAB TO CLEAR THE SPOIL. Footway will be open at all times or walk way provided. |
Responsibility for works: Scottish and Southern Power Distribution |
Current status: Planned work about to start |
Works reference: LP551S30002020 |
|
B455 Scotch Common, West Ealing |
08 October — 11 October |
Delays likely Traffic control (Stop/Go boards) |
Works description: EXCAVATION - install 2 cab foundations and ducting (trench).50mb of pedestrian management barriers will be around the workarea, to allow footpath for the pedestrians to remain open, there will also be Stop/Go to controll the traffic. when the stop/go removes at 15:30 the work area will be barriered off with 50mb |
Responsibility for works: Vodafone |
Current status: Planned work about to start |
Works reference: NX04178464-RTS-KL |
|
Cedar Grove, Ealing |
08 October — 13 October |
Delays likely Road closure |
Works description: new customer water supply 2x25mm MDPE mtrd, works in the footway and inCarriageway. Our intention is to complete the Permanent Reinstatement inthe same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000807057030100-001 |
|
Park Parade, Acton |
08 October — 13 October |
Delays likely Road closure |
Works description: new customer water supply 1x32mm MDPE mtrd, works in the footway and inCarriageway. Our intention is to complete the Permanent Reinstatement inthe same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000807668760045-001 |
|
The Park, Ealing |
08 October — 20 October |
Delays likely Road closure |
Works description: Excavate & connect to CGL Gas Main providing gas supply to new housing development. Approx dimensions: 65m x 0.5m carriageway. Depth: 0.8m. FIRST TIME PERM |
Responsibility for works: GAS TRANSPORTATION CO LTD |
Current status: Planned work about to start |
Works reference: ZP00768351/EPLR |
|
A4020 Uxbridge Road, Ealing |
10 October — 13 October |
Delays likely Lane closure |
Works description: 27/020 tel0197366 - slot cut c/w sensor loops to repair traffic signals SD6 repair feeder plus feed to existing chamber, 10.00-15.00, westbound c/w swapping lane 1 & 2 and f/w to chamber (ped access maintained) |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG516S000000004188 |
|
A4020 Uxbridge Road, Hanwell |
10 October — 11 October |
Delays likely Traffic control (multi-way signals) |
Works description: S81 PLANNED COVER REPLACEMENT--WORKS INTENDED TO INCLUDE FIRST TIME PERMANENT REINSTATEMENT WITHIN SAME PHASE |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU026002141DCQY--000004 |
|
A406 North Circular Road, Park Royal |
10 October — 12 October |
Delays likely Lane closure |
Works description: BLOCK CLOSURE EB# TESTING LIGHTS& BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431316642 |
|
A406 North Circular Road, Park Royal |
10 October — 12 October |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS& BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431316659 |
|
B455 Haven Green, Ealing |
10 October — 13 October |
Delays likely Lane closure |
Works description: 27/247 tel0198044 - slot cut c/w sensor loops to repair traffic signals SD3 & SD4 repair feeder plus feed to existing chamber, 10.00-15.00, northbound c/w swapping lane 1 & 2 and f/w to chamber (ped access maintained) |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG516S000000004190 |
|
A4020,B455 The Broadway, Ealing |
12 October — 13 October |
Delays likely Lane closure |
Works description: 27/018 tel0182742 - slot cut c/w sensor loops to repair traffic signals SD2 repair feeder plus feed to existing chamber, To install ducting & underkerb, 10.00-15.00, eastbound c/w lane 1 and f/w to chamber (ped access maintained) |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG516S000000004192 |
|
A4020 The Mall, Ealing |
12 October — 13 October |
Delays likely Lane closure |
Works description: 27/018 tel0182742 - To install ducting & underkerb for TfL traffic signal loops, 10.00-15.00, westbound c/w lane 1 and f/w to chamber (ped access maintained) Bus Stop: 733 Suspension |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG516S000000004191 |
|
A406 Gunnersbury Avenue (north Circular Road) |
12 October — 14 October |
Delays likely Lane closure |
Works description: BLOCK CLOSURE NB# TESTING LIGHTS& BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431316682 |
|
A406 Gunnersbury Avenue (north Circular Road) |
12 October — 14 October |
Delays likely Lane closure |
Works description: BLOCK CLOSURE SB# TESTING LIGHTS& BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431316678 |
|
A406 North Circular Road, Park Royal |
11 October — 13 October |
Delays likely Lane closure |
Works description: BLOCK CLOSURE EB# TESTING LIGHTS& BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431316663 |
|
A406 North Circular Road, Park Royal |
11 October — 13 October |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS& BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431316668 |
|
B452,B455 Argyle Road, West Ealing |
12 October — 17 October |
Delays likely Traffic control (multi-way signals) |
Works description: Valve Repack 0 to 6" in Carriageway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031144221-001 |
|
B4491 Little Ealing Lane, Ealing |
04 October — 11 October |
Delays likely Traffic control (two-way signals) |
Works description: LAY NEW SERVICE 2M FROM MAIN IN FOOTWAY |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000757666 |
The Park, Ealing |
01 September — 31 October |
Delays likely Road closure |
Works description: Carriageway resurfacing, |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV00665000548 |
|
B452,B455 Argyle Road, West Ealing |
28 August - 31 October |
Delays likely Road closure |
Works description: Carriageway resurfacing, including some areas of carriageway reconstruction. |
Responsibility for works: Ealing |
Current status: Planned work about to start |
Works reference: DV00665000536 |
3rd October 2018
|