Forthcoming Roadworks in the Ealing Area
Closures and diversions which may cause problems
![Forthcoming Roadworks in The Ealing Area](/image/ealingtoday/info/images/roadclosed.jpg)
A406 Gunnersbury Avenue (north Circular Road) |
18 June — 27 June |
Delays likely Lane closure |
Works description: Phase 5 - 8 Surfacing Works - S58 required |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG432351166 |
|
A40 Western Avenue, Greenford |
17 June — 18 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368244 |
|
A40 Western Avenue, Greenford |
17 June — 18 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368233 |
|
A40 Western Avenue, Greenford |
18 June — 19 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368252 |
|
A40 Western Avenue, Perivale |
17 June — 18 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368243 |
|
A40 Western Avenue, Perivale |
17 June — 18 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368236 |
|
A40 Western Avenue, Perivale |
18 June — 19 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368250 |
|
A40 Western Avenue, Perivale |
19 June — 20 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368266 |
|
A40 Western Avenue, Perivale |
19 June — 20 June |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368264 |
|
B452,B455 Argyle Road, West Ealing |
17 June — 17 June |
Delays likely Traffic control (two-way signals) |
Works description: S81 PLANNED COVER REPLACEMENT--WORKS INTENDED TO INCLUDE FIRST TIME PERMANENT REINSTATEMENT WITHIN SAME PHASE |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU026002141HLLG--000003 |
|
B455 South Ealing Road, Ealing |
19 June — 19 June |
Delays likely Traffic control (multi-way signals) |
Works description: excavation works - telecoms cabinet swap - hiab in carriageway, three way traffic lights to be used |
Responsibility for works: O2 (UK) Limited |
Current status: Planned work about to start |
Works reference: MG08043832/CLS/SJTM1 |
|
Chepstow Road, Hanwell |
17 June — 21 June |
Delays likely Road closure |
Works description: Serv Pipe Relay Ex Fitting Sz P Cway & Fway in Carriageway. Ourintention is to complete the Permanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031279793-001 |
|
Leighton Road, West Ealing |
17 June — 19 June |
Delays likely Road closure |
Works description: Valve Repack 0 to 6" in Carriageway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031265219-001 |
|
Madeley Road, Ealing |
17 June — 01 September |
Delays likely Traffic control (two-way signals) |
Works description: Highway improvement scheme |
Responsibility for works: Ealing |
Current status: Advanced planning |
Works reference: DV00665000819 |
|
Mattock Lane, West Ealing |
17 June — 19 June |
Delays likely Road closure |
Works description: Service Pipe Repair in Carriageway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031255891-002 |
|
Mattock Lane, West Ealing |
17 June — 19 June |
Delays likely Road closure |
Works description: Service Pipe Repair in Carriageway. Our intention is to complete thePermanent Reinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU301000031255891-001 |
|
B455 South Ealing Road, Ealing |
10 June — 22 October |
Delays likely Traffic control (multi-way signals) |
Works description: IMGA202336. Replace approximately 1179metres of 14in Cast IronLowPressure gas main with new 355mm PE main by means of insertion.This will include several connections and all services on the street. |
Responsibility for works: Cadent |
Current status: Planned work about to start |
Works reference: AZ0071000838110 |
A406 Gunnersbury Avenue (north Circular Road) |
01 May — 31 August |
Delays likely Lane closure |
Works description: EXCAVATE TRENCH INSTALL CABLE CARRY OUT JOINTING BACKFILL AND REINSTATE |
Responsibility for works: Scottish and Southern Power Distribution |
Current status: Advanced planning |
Works reference: LP705S30001055 |
|
A4000, A40 Western Avenue, Acton |
27 February — 23 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342348 |
|
Westway, Hammersmith and Fulham |
27 February — 23 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342350 |
|
June 18, 2019
|