Where to expect traffic delays in the days ahead
        B408 Askew Road 
      21 August — 22 August Delays likely Traffic control (Stop/Go boards)
      Works description: Thames Water need to carry out works on the water valve. Stop & Go boards will be installed to allow these works to be carried out. Minor Works, No Excavation. 
      Responsibility for works: THAMES WATER 
      Current status: Planned work about to start 
      Works reference: MU150WO-23681839/TW/01 
B408 Paddenswick Road
      20 August — 01 October Delays likely Traffic control (multi-way signals) 
      Works  description: CONSTRUCTION OF A MINI PUMPING STATION (FLIP) IN THE FOOTWAY & CARRIAGEWAY
      Responsibility for works: THAMES WATER 
      Current status: Planned work about to start 
      Works reference: MU895MGJV/FLIPS/193360A 
 A3220 Holland Road
      20 August — 21 August Delays likely Lane closure 
      Works description: 11/091 TEL0192550 - Access TfL traffic signal pole 7, B phase red aspect Siemens led lv type out needs replacing. 00:01-05:00. NW/B lane 4. Short stay works, approx 15 mins on site. No noisy works involved 
      Responsibility for works: Transport for London 
      Current status:Planned work about to start 
      Works reference: YG516S000000004077 
Information supplied by roadworks.org
August 20, 2018
  |